The MachineRecord
RegistryTMR-0966

Trelleborg's Navya self-driving bus line stopped for about five months, partly because the bus could not reliably determine its position

No harmmalfunctionautonomous vehicleNavya
Date of incident
November 2022
Sources place this in the month, not on a day.
Location
Akka, Trelleborg, Sweden
Model
Navya self-driving bus
Sources
1
EscalationReport

Established by the operator's own report to a regulator, obtained through a public records request and quoted on its document page, linked below.

Timeline

How the event developed

  1. 2023-10-23Report

    Trelleborg municipality reported to Transportstyrelsen that the line could not run from November 2022 to April 2023, partly because the bus could not establish its position and was not safe in traffic.

    themachinerecord.com
Sources

Every claim above traces to one of these

Links are never hidden behind a paywall of ours. Where a copy of the page exists it is linked beside the source with the date it was taken, because news links rot and a dead link next to a saved copy is still evidence. Some copies predate this register: they were made by the Internet Archive before we existed, and the date shown is the date of that copy, not of our visit.

    One source, and it is the whole basis of this case: the operator's own report to a regulator, obtained through a public records request, rather than reporting about the event. The two independent domains the news rules require do not apply here, because the report is the operator's own account as filed with the regulator, not a retelling of it.

  • themachinerecord.comTrelleborg final report on the self-driving bus project (TSV 2021-4588)2023-10-23no copytier 2
Weekly digest

New cases, once a week, by email

Every case added to the register in the last seven days, with its sources. Free, no account, and the register is the only sender.

One email a week, Monday morning. Unsubscribe in one click.

Keep watching

Follow Navya

An email the moment a new case lands on Navya or this one gains a development, or the full record on the company as one document with archived copies of its sources.

Right of reply