Trelleborg final report on the self-driving bus project (Akkaslingan)
Final report of the Navya self-driving bus line in the Akka area of Trelleborg, September 2022 to June 2023. Between November 2022 and April 2023 the line could not run, partly because the bus could not reliably determine its own position.
The record
- Original title
- Slutredovisning av projektet självkörande buss i Trelleborg
- Written by
- Trelleborgs kommun
- Date
- 23 October 2023
- Pages
- 8
- Held by
- Transportstyrelsen (Swedish Transport Agency)
- Case number
- TSV 2021-4588
- Released to us
- 26 November 2026, under the Swedish principle of public access to official records (offentlighetsprincipen)
- Withheld passages
- None marked.
- How to get a copy
- Anyone can ask Transportstyrelsen for a copy of these public records, citing the case number (diarienummer) given on each document page, at kontakt@transportstyrelsen.se.
Passages the register relies on
Trelleborgs kommun tillsammans med Bergkvarabuss och Skånetrafiken testade självkörande teknik i form av en buss i Akka området från september 2022 till juni 2023. Test utfördes med buss från franska bolaget NAVYA och trafikerade Akkaslingan som gick längs med Nils Holgerssons väg, samt till äldreboende Täppan och busshållplats Trelleborg Akka.
Trelleborg municipality, together with Bergkvarabuss and Skånetrafiken, tested self-driving technology in the form of a bus in the Akka area from September 2022 to June 2023. The test used a bus from the French company NAVYA and ran the Akkaslingan line along Nils Holgerssons väg, to the Täppan care home and the Trelleborg Akka bus stop.
Page 1
Mellan november 2022 och april 2023 uppstod flera utmaningar med fordonet som ledde till att linjen inte kunde trafikeras. Några av utmaningarna var att tekniken i bussen hade svårt att säkerställa bussens position vilket gjorde att den inte var trafiksäker, samt svårigheter med laddningen.
Between November 2022 and April 2023 several problems with the vehicle meant the line could not run. Among them, the bus's technology had difficulty establishing the bus's position, which made it unsafe in traffic, and there were difficulties with charging.
Page 1
Mitt under projektet i januari 2023 meddelade NAVYA att de hade ekonomiska problem och ansökt om rekonstruktion. Detta gjorde att det inte gick att få ta i några reservdelar eller reparatörer under en längre tid.
In the middle of the project, in January 2023, NAVYA announced financial problems and applied for reorganisation. This meant no spare parts or repairers could be obtained for a long time.